#2308 had its second round of inspections Tuesday (building inspection code 130 for anyone wondering). We passed! This time around, the DCRA inspector focused on the additions’ foundation; the first inspection evaluated foundation footings. Confused as to what is what?! I was, too. I continue to learn the terms, the processes, and the steps involved in building new construction, even if attached to an existing structure. What I’ve learned so far is outlined below, in pictures.

The first four pictures show footing construction, with vertical rebar being installed. Rebar, I’ve learned, needs to be grouted solid to become integral to the wall.

img_6529

img_6288    img_6287img_6289

The next set of pictures show the start of waterproofing. The black, tar-like material is used to prevent dampness. A drainage board (last picture) is also being installed to provide adequate waterproofing.

img_6433      20180821_153017863_iOS

More to come!

One thought on “Laying a Foundation #LittleK

Add yours

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

Blog at WordPress.com.

Up ↑

%d bloggers like this: